关键链技术下地铁项目施工缓冲区优化研究

Research on optimization of metro project construction buffer area based on critical chain technology
下载PDF
导出
摘要 缓冲区的确定关系到整个地铁施工项目的时间进度。目前,国外和国内学者对研究关键链技术的兴趣较浓厚,而对缓冲区的确定方法仍缺乏进一步深入。通过分析前人研究的内容,结合地铁施工项目实际进展提出与进度吻合的缓冲区确定方法。首先,结合分段模糊工期研究缓冲区时间大小;其次,考虑不确定影响因素计算资源综合约束系数;最后提出符合地铁施工项目的缓冲区确定方法,并通过案例对提出的方法进行说明。 The determination of the buffer zone is related to the time schedule of the entire subway construction project. At present, foreign and domestic scholars are more interested in researching critical chain technology, but there is still a lack of further in-depth methods to determine the buffer zone. This article will analyze the content of previous studies and combine the actual progress of the subway construction project to propose a buffer determination method that is consistent with the schedule. First, study the size of the buffer zone in combination with the segmented fuzzy construction period, secondly, consider the uncertain factors to calculate the comprehensive resource constraint coefficient, finally, the method for determining the buffer zone in accordance with the subway construction project is proposed, and the proposed method is explained through a case.
作者 林尚月 Lin Shangyue(China Railway 14th Bureau Group Co.,Ltd.,Beijing 250101,China)
出处 《山西建筑》 2022年第14期122-127,共6页 Shanxi Architecture
关键词 关键链 地铁施工项目 缓冲区 分段模糊工期 critical chain subway construction project buffer zone subsection fuzzy construction period
  • 相关文献

参考文献8

二级参考文献58

  • 1白思俊.活动网络计划约束的复杂性度量及其应用[J].航空学报,1994,15(7):891-894. 被引量:6
  • 2刘士新,宋健海,唐加福.资源受限项目调度中缓冲区的设定方法[J].系统工程学报,2006,21(4):381-386. 被引量:70
  • 3Goldratt E M.Critical Chain[M].Great Barrington:The North River Press,1997.
  • 4Hagemann A G.Use of the Critical Chain Project Management Technique at NASA,Langley Research Center[C].AIAA/IEEE Digital Avionics Systems Conference-Proceedings,2001,Oct,14-18:4B11-4B110.
  • 5Rand G K.Critical chain:The theory of constraints applied to project management[J].International Journal of Project Management,2000,18:173-177.
  • 6Steyn H.An investigation into the fundamentals of critical chain project scheduling[J].International Journal of Project Management 2000,19:363-369.
  • 7Herroelen W,Leus R.On the merits and pitfalls of critical chain scheduling[J].Journal of Operations Management,2001,19:559-577.
  • 8Wei C,Liu P,Tsai Y.Resource-constrained project management using enhanced theory of constraint[J].International Journal of Project Management,2002,20:561-567.
  • 9Yeo K T,Ning J H.Integrating supply chain and critical chain concepts in engineer-procure-construct (EPC) projects[J].International Journal of Project Management,2002,20:253 -262.
  • 10Brucker P,Drexl A,Mohring R,et al.Resource-constrained project scheduling:Notation,classification,models,and methods[J].European Journal of Operational Research,1999,112:3-41.