摘要
针对一起500 kV同塔双回重要输电线路发生的跳闸故障,结合故障塔的巡检情况和设计参数,使用了现场检查、故障塔塔头电气间隙校核、接地电阻测量、雷击风险评估等方法,对故障原因进行了排查及综合分析,判断了雷击放电的原因,并提出了线路防雷改造措施,为其他线路的长间隙雷击放电故障分析提供参考。
Aimed at analyzing a tripping fault of an important 500 kV double-circuit transmission line on the same tower, and combined with the inspection information and design parameters of the faulty tower, methods such as field inspection, check of the electrical gap of the top hamper of the faulty tower, grounding resistance measurement and lightning stroke risk assessment are used to investigate and comprehensively analyze the cause of the fault, and to judge the cause of the lightning-induced discharge. Lightning protection modification measures of the transmission line are proposed to provide a reference point for the analysis of the long air gap lightning discharge fault of other lines.
作者
毛强
呙锴
MAO Qiang;GUO Kai(Maintenance and Test Center,CSG EHV Power Transmission Company,Guangdong Guangzhou 510663,China)
出处
《广西电力》
2022年第1期58-62,共5页
Guangxi Electric Power
关键词
同塔双回线路
雷击故障
塔头间隙校核
反击
绕击
雷击跳闸率
double-circuit transmission line on the same tower
lightning fault
top hamper gap check
flashback
shielding failure flashover
lightning outage rate