摘要
在10kV配电线路工作中,工作人员经常需要使用收线盘对导线进行架设与回收。然而,现有的收线盘形状尺寸固定,并且收线盘旋转后只能通过人手使用木棍操作放线盘来实现降速,容易对操作人员造成误伤。文章提出一种配网架空导线收放装置,用于解决现有的收线盘形状大小固定且降速时存在安全风险的问题。
In the work of 10kV distribution lines,workers often need to use the take-up reel to erect and recover the wires.However,the shape and size of the existing take-up reel are fixed,and after the take-up reel is rotated,the speed can only be reduced by manipulating the take-up reel with a wooden stick,which is likely to cause accidental injury to the operator.This paper proposes a distribution network overhead conductor retraction device,which is used to solve the problem that the shape and size of the existing take-up reel is fixed and there is a safety risk when the speed is reduced.
作者
聂洪强
梁焕平
李乐恩
NIE Hongqiang;LIANG Huanping;LI Le'en(Jiangmen Power Supply Bureau,Guangdong Power Grid Co.,Ltd.,Jiangmen 529000,China)
关键词
架空导线
收放
配电线路
线盘
降速
overhead conductor
retractable
distribution line
reel
speed reduction