燃煤电站350 MW机组FCB演示试验实施策略 被引量:2

Implementation Strategy of FCB Demonstration Test for a 350 MW Coal-fired Unit
下载PDF
导出
摘要 介绍了海外某燃煤电站350 MW机组FCB演示试验实施过程,基于机组FCB功能的配置要求,通过设计变更及控制逻辑优化,成功实现了相关功能。针对试验过程中存在的不足,提出了改进措施,并对燃煤电站FCB试验提出建议,为国内电力企业开拓国际市场提供借鉴。 The implementation of the FCB demonstration test for a 350 MW unit in an oversea coal-fired power station is introduced.Based on the configuration requirements of the unit’s FCB functions,the relevant functions were successfully realized through design changes and control logic optimization.In view of the deficiencies in the test process,improvement measures were put forward,as well as suggestions for the FCB test of coal-fired power plants,which offers reference for domestic power companies to expand international markets.
作者 贤建伟 XIAN Jianwei(Shanghai Electric Wind Power Group Co.,Ltd.,Shanghai 200233)
出处 《电力安全技术》 2022年第6期47-50,共4页 Electric Safety Technology
关键词 燃煤电站 350 MW机组 快速甩负荷 配置优化 coal-fired power station 350 MW unit fast cut-back optimization of configuration
  • 相关文献

参考文献4

二级参考文献12

共引文献38

同被引文献17

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部