新安装的变压器必须带负荷检查差动保护电流回路接线正确后才能正式投运。针对现场没有足够用电负荷的情况,提出2种变压器简单有效的一次回路通流方法,以保证变压器一次性投运成功。
The newly installed transformer must be put into operation after checking the correct wiring of differential protection current circuit with load.In view of the situation that there is not enough power load on site,two simple and effective primary circuit current passing methods of transformer are proposed to ensure the successful operation of transformer at one time.
作者
谌铮松
曾玉章
CHEN Zhengsong;ZENG Yuzhang(Shenzhen Branch,CNOOC Energy Development Equipment Technology Co.,Ltd.,Shenzhen 518000,China;CNOOC Huizhou Petrochemical Co.,Ltd.,Huizhou 516086,China)
出处
《电工技术》
2022年第11期105-106,109,共3页
Electric Engineering
关键词
变压器
差动保护
电流回路
一次回路通流
transformer
differential protection
current circuit
primary circuit current