摘要
福建山美水电站地下厂房于2012年实行“无人值守”运行值班方式,在实行前进行了充分的论证探讨,就设备、技术、运行管理、预防性措施等工作做了充分的准备。文章对山美电站实行“无人值守”前的各项准备工作进行总结分析,为同类水电站实行“无人值守”前期准备工作提供相关经验。
The underground powerhouse of Fujian Shanmei Hydropower Station implemented the“unattended”operation duty mode in 2012.Sufficient demonstration and discussion were carried out before implementation,and sufficient preparations were made on equipment,technology,operation management,preventive measures,etc.The preparatory work before the implementation of“unattended”task in Shanmei Hydropower Station is summarized and analyzed in the paper,thereby providing reference experience for the preparatory work of similar hydropower stations.
作者
陈晓明
CHEN Xiaoming(Quanzhou Shanmei Reservoir Water Resource Allocation Center,Quanzhou 362000,China)
出处
《中国水能及电气化》
2022年第6期56-58,63,共4页
China Water Power & Electrification
关键词
山美电站
无人值守
前期准备工作
Shanmei Power Station
unattended
preparatory work