期刊文献+

市域铁路装配式整孔现浇箱梁支架施工技术 被引量:2

Construction Technology of Assembled Whole Hole Cast-In-PlaceBox Girder Support for Municipal Railway
下载PDF
导出
摘要 市域铁路线路受市区空间和郊区农田地质影响,传统满堂支架存在局限性,“钢管柱+贝雷支架”的综合型方案适应性更强,可以形成流水化作业模式,使各项工作沿着计划有序推进。着重对市域铁路装配式整孔现浇箱梁支架施工技术展开探讨,提出一些具体的技术应用要点,旨在为类似项目提供参考。 In order to meet the requirements of residents'traffic travel,the scale of urban railway construction expands accordingly.In actual construction,viaduct construction is usually adopted in order to reduce the occupation of the ground,and cast-in-place beam is the main construction method.Urban railway line is affected by urban space and suburban farmland geology,traditional full support has limitations,“steel pipe column+Beret support”comprehensive scheme is more adaptable,can form flow operation mode,so that all work along the plan orderly advance.In this paper,the construction technology of assembled full-hole cast-in-place box girder support for municipal railway is discussed emphatically,and some specific technical application points are put forward in order to provide reference for similar projects.
作者 李新 LI Xin(China Railway 16 th Bureau Group Co.,Ltd.,Beijing 100018,China)
出处 《黑龙江交通科技》 2022年第6期128-130,共3页 Communications Science and Technology Heilongjiang
关键词 市域铁路 现浇箱梁支架 装配式 municipal railway cast-in-place box girder support prefabricated
  • 相关文献

参考文献1

二级参考文献3

同被引文献11

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部