摘要
为提高路基沉降预测的精度和可靠性,以改进Gompertz模型和灰色Verhulst模型为单一模型构建了一种基于诱导有序加权几何平均算子的组合预测模型,并结合工程实测路基沉降数据对组合预测模型的有效性和可靠性进行验证。结果表明:深圳滨海大道的实例中组合预测模型的预测精度指标MAE分别比两个单一模型提高53.91%和87.97%,可靠性指标SPE分别比两单一模型提高50%和87.88%。较之单一预测模型,基于IOWGA算子的改进Gompertz-灰色Verhulst组合预测模型预测精度和可靠性更高,适应性更强。
In order to improve the precision and reliability of subgrade settlement prediction,a combined prediction model based on induced ordered weighted geometric average operator is constructed by improving Gompertz model and Grey Verhulst model,the validity and reliability of the combined prediction model are verified by the measured settlement data of subgrade.The results show that in the case of Shenzhen Binhai Avenue,the MAE(prediction accuracy index)of the combined forecasting model is 53.91% and 87.97% higher than that of the two single models,respectively,and the SPE(reliability index)is 50% and 87.88% higher than that of the two single models,respectively.Compared with the single prediction model,the improved Gompertz-Grey Verhulst combined forecasting model based on IOWGA operator has higher prediction accuracy,reliability and adaptability.
作者
杨雨
邱红胜
李东健
罗刚
YANG Yu;QIU Hong-sheng;LI Dong-jian;LUO Gang(School of Transportation and Logistics Engineering,Wuhan University of Technology,Wuhan 430063,China)
出处
《武汉理工大学学报》
CAS
2022年第4期36-42,63,共8页
Journal of Wuhan University of Technology
基金
国家自然科学基金(11672215).
关键词
等时距处理
IOWGA算子
路基沉降预测
组合预测模型
equidistant processing
IOWGA operator
subgrade settlement prediction
combined forecasting model