摘要
本文以在建的台州市域铁路S1线羊头山隧道与杭绍台高铁下北山隧道为例,两隧道上下并行,最近水平距离12.45m,最小垂直距离2.46m,本文探讨了两隧道施工时序,通过全过程施工工况分析总结,探讨了并行隧道施工时序影响问题。
This paper takes the Yangtoushan Tunnel of Taizhou Municipal Railway S1 Line and the Xiabeishan Tunnel of Hangshaotai High-speed Railway as examples.The two tunnels are parallel up and down.The nearest horizontal distance is 12.45m and the minimum vertical distance is 2.46m.This paper discusses the construction sequence of the two tunnels.Through the analysis and summary of the whole process of construction conditions,the influence of parallel tunnel construction timing is discussed.
作者
赵耀
ZHAO Yao(Jiangsu CRRC City Development Co.,Ltd.,Wuxi 214104,China)
出处
《价值工程》
2022年第24期68-71,共4页
Value Engineering
关键词
矿山法隧道
上下并行施工
施工时序
监测
措施
mine tunnel
parallel construction up and down
construction sequence
monitoring
measures