期刊文献+

胜利一号露天煤矿采区过渡方式研究 被引量:2

Study on the mining area steering scheme of Shengli No.1 Open-pit Coal Mine
下载PDF
导出
摘要 针对胜利一号露天矿首采区向二采区过渡的问题,提出了“L”缓帮过渡、扇形过渡及重新拉沟3种采区过渡方案,将此3种过渡方式又划分为“连续式”和“间断式”2种过渡类型,并对“连续式”过渡类型中“L”型转向和扇形转向2种采区转向方案的演化过程和经性济进行对比分析,得出胜利一号露天煤矿采用采区扇形转向方案为最优采区过渡方案,此方案无需增加额外排土空间,生产过渡顺畅,生产规模稳定,可为矿山生产企业创造更多的经济效益。 Aiming at the problem of the initial mining area steering to the second mining area in Shengli No.1 Open-pit Coal Mine,the article presents"L"steering,sector steering and re-ditching,which are divided into continuous type and discontinuous type.The article compares the evolution process and economic economy of the two modes of continuous transition,obtains that the optimal transition method of open-pit coal mine is the sector steering scheme.The steering scheme achieves the goal of creating economic benefits for the production enterprise without increasing the external dump space,smoothing the production transition,stabilizing the production scale.
作者 张洪 蔡忠超 ZHANGHong;CAI Zhongchao(China Coal Technology and Engineering Group Shenyang Design&Research Institute,Shenyang 110015,China)
出处 《露天采矿技术》 CAS 2022年第4期14-18,共5页 Opencast Mining Technology
关键词 露天煤矿 采区划分 开采顺序 过渡方式 扇形过渡 open-pit coal mine mining area division mining sequence steering mode sector steering
  • 相关文献

参考文献6

二级参考文献24

共引文献78

同被引文献24

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部