摘要 以台州市域铁路S1线开发大道站对影响地下连续墙施工的大直径钢筋混凝土污水管线清障施工为背景,提出了在污水管线未迁改完成的情况下采用明挖方式对地下污水管线进行清障的施工工艺,实现了将钢筋混凝土污水管道完整挖出,清障效果好且能兼顾后续地下连续墙施工。相较于常用的液压振动捶破碎管道或旋挖钻机破碎管道清障施工方式,避免了残留钢筋或清障不彻底对后续地下连续墙施工产生影响。 Based on the obstacle removal construction of large-diameter reinforced concrete sewage pipeline affecting the construction of underground diaphragm wall at Kaifa Avenue station of Taizhou City railway line S1,this paper puts forward the construction technology of using open excavation to remove the obstacle of underground sewage pipeline without the completion of relocation of sewage pipeline, so as to realize the complete excavation of reinforced concrete sewage pipeline. The barrier removal effect is good, and the follow-up diaphragm wall construction can be taken into account. Compared with the commonly used construction methods of hydraulic vibrationhammer breaking pipeline or rotary drilling rig breaking pipeline obstacle removal, it avoids the impact of residual reinforcement or incomplete obstacle removal on the subsequent construction of diaphragm wall.
作者 赵海川 钱栋栋 王礼武 Zhao Hai-chuan;Qian Dong-dong;Wang Li-wu
出处 《建筑技术开发》 2022年第16期39-42,共4页 Building Technology Development
关键词 地下连续墙 钢筋混凝土污水管道 深埋 大直径 清障施工 diaphragm wall reinforced concrete sewage pipe deep burial large diameter obstacle removal construction
  • 相关文献

参考文献2

二级参考文献7

共引文献9

同被引文献47

引证文献7

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部