摘要
为优化多站融合系统的运行,以提高系统运行经济性、环保性、消纳率为优化目标,对多站融合系统进行研究分析。构建包含光伏电站、风机、储能电站以及多种负荷的多站融合系统优化模型并建立约束条件。改进了NSGA-Ⅱ算法,在传统NSGA-Ⅱ算法的基础上引入量子搜索以进一步提高搜索能力,在算法中利用蒙特卡洛模拟生成随机参数,从而求解包含多重不确定性的运行优化问题。以某地多站融合数据为例进行仿真分析,并与传统的粒子群算法以及未改进的NSGA-Ⅱ算法进行对比,算例验证所提方法能够提升多站融合系统的运营效益。
In order to effectively improve the economy of multi-station integration construction, based on ensuring the power supply reliability and new energy consumption of the system, a multi-station integration capacity optimal allocation model with levelized energy cost as the optimization objective is established, and a multi-station integration capacity optimal allocation method considering multiple uncertainties to solve the stochastic optimization model is proposed. The simulation results of multi-station fusion data show the effectiveness of the proposed method and model.
作者
李雪
周航
路晓敏
张景晨
陶以彬
胡安平
LI Xue;ZHOU Hang;LU Xiaomin;ZHANG Jingchen;TAO Yibin;HU Anping(Nanjing Electric Power Supply Company,State Grid Jiangsu Electric Power Co.,Ltd.,Nanjing 210019,China;China Electric Power Research Institute,Nanjing 210003,China)
出处
《电力需求侧管理》
2022年第5期97-101,共5页
Power Demand Side Management
基金
国网江苏省电力有限公司科技项目(J2020089)。
关键词
多站融合
运行优化
NSGA-Ⅱ算法
量子搜索
multi-station integration
NSGA-Ⅱalgorithm
operation optimization
quantum search