含水砂卵石地层竖井换刀施工安全技术

CONSTRUCTION SAFETY TECHNOLOGY FOR TOOL CHANGING IN SHAFT IN WATER-BEARING SANDY PEBBLE STRATUM
下载PDF
导出
摘要 如何在安全和经济效益下快速进行盾构机刀具检修或更换,成为制约盾构是否顺利掘进、能否提高掘进效率的关键问题。北京地铁6号线4标慈寿寺站–花园桥站盾构区间工程,通过4次小竖井结合地层加固的辅助施工方法,在不开仓的情况下,快速完成了刀盘刀具的检修更换施工作业,取得了良好的效果,值得进一步推广和借鉴。 How to rapidly maintain or replace the shield machine tools in a safe&economic manner becomes a key issue to restrict the smooth tunneling and improve the tunneling efficiency.In the section Cishousi Station~Huayuanqiao Station in Bid 4#of Beijing Subway Line 6,tool maintenance and replacement are rapidly completed without opening the magazine by adopting the auxiliary construction method of 4 small shafts in combination with stratum reinforcement and favorable effects are realized.This technology is worthy of further popularization and reference.
作者 赵欣 ZHAO Xin(BCEG Civil Engineering Co.,Ltd.,100015,Beijing,China)
出处 《建筑技术》 2022年第9期1163-1165,共3页 Architecture Technology
关键词 盾构 砂卵石 刀具 检修更换 shield sand pebbles tool maintenance&replacement
  • 相关文献

参考文献2

二级参考文献1

  • 1叶康慨.超前地质加固在盾构施工中的应用[J].现代隧道技术,2004,(S):514-518.

共引文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部