摘要 悬臂浇筑的连续梁(刚构)桥施工中须设置施工预拱度,该预拱度的设置有多种影响因素。通过分析与实例计算结果表明,这些影响因素中容易被计算者忽视的施工阶段划分方式恰恰是对施工预拱度的设置具有决定作用的因素。 Construction precamber must be set in the construction of cantilevered casting continuous beam(rigid frame)bridge,and the setting of precamber has many influence factors.The analysis and example calculation results show that among these influencing factors,the construction stage division method,which is easily overlooked by the calculator,is the decisive factor for the setting of the construction precamber.
作者 董毓 Dong Yu(Shengzhou Chengnan Construction Investment Co.,Ltd.,Zhejiang Shengzhou,312400,China)
出处 《石家庄铁路职业技术学院学报》 2022年第3期43-47,共5页 Journal of Shijiazhuang Institute of Railway Technology
关键词 悬臂施工 预拱度设置 施工阶段划分 cantilever casting construction precamber setting construction stage division
  • 相关文献

参考文献6

二级参考文献58

共引文献21

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部