杨房沟水电站高拱坝大体积混凝土温控措施研究 被引量:2

Temperature Control Measures of Mass Concrete in High Arch Dam in Yangfanggou HEP
下载PDF
导出
摘要 高拱坝大体积混凝土施工过程中的温度控制为其重中之重。为解决大体积混凝土在其硬化过程中水泥水化热在块体内产生的温度变化带来的应变和应力、继而引发的温度裂缝问题,需要采取强有力的施工措施控制混凝土的温度变化。阐述了杨房沟水电站从混凝土原材料、出机口温度、混凝土入仓、浇筑、养护及通水冷却等环节进行的全过程有效控制,使混凝土温控相关的各项指标满足设计要求,控制水平优秀,所取得的经验对同类工程具有推广和借鉴意义。 Temperature control of mass concrete during construction is a top priority in high arch dam.In order to meet the challenge of strain and stress caused by the temperature change of cement hydration heat in the mass concrete during its hardening process and the temperature crack caused by it,it is necessary to take strong construction measures to control the temperature change of concrete.This paper elaborates the effective control of the whole process in Yangfanggou hydropower project,from concrete raw materials,outlet temperature,concrete placing,pouring,curing to water cooling,so as to make the relevant indicators of concrete temperature control meet the design requirements,and the control level is excellent.The experience obtained has the significance of promotion and reference for similar projects.
作者 叶劲松 刘晓龙 李雷刚 YE Jinsong;LIU Xiaolong;LI Leigang(Sinohydro Bureau 7 Co.,Ltd,Chengdu,Sichuan 610213)
出处 《四川水力发电》 2022年第4期10-14,共5页 Sichuan Hydropower
关键词 高拱坝 大体积混凝土 杨房沟水电站 温度 控制措施 研究 high arch dam mass concrete Yangfanggou Hydropower Project Temperature Control measure study
  • 相关文献

参考文献3

二级参考文献9

共引文献11

同被引文献19

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部