110kV变电站架空输电线路工程施工作业是当前输电线路建设不能缺少的一部分。紧线施工作业对塔杆、环境质量要求较高,如果这方面存在问题严重影响紧线施工效果。论文通过对架空输电线路工程施工要求进行分析,探讨变电站架空输电线路工程紧线施工面临的问题和解决措施。
The construction of overhead transmission line project in 110kV substation is an indispensable part of current transmission line construction.Stringing construction has higher requirements on tower pole and environmental quality,if there are problems in this aspect,the construction effect will be seriously affected.Based on the analysis of the construction requirements of overhead transmission line project,this paper discusses the problems and solutions of tight line construction of overhead transmission line project in substation.
作者
陈嘉亮
Jialiang Chen(China Energy Engineering Group Guangdong Power Engineering Co.,Ltd.,Guangzhou,Guangdong,510700,China)
出处
《工程设计与施工》
2020年第9期42-44,共3页
Engineering Design and Construction
关键词
变电站
架空线路
输电线路
紧线施工
substation
overhead line
transmission line
tight line construction