摘要
以上海大芦线航道整治二期工程大团惠南段跨河钢系杆拱桥为例,结合施工环境,详细介绍了钢系杆拱桥的主要施工工艺,分析和总结了施工过程中的重点和难点。该桥梁采用“先梁后拱”、“浮吊工艺”,施工过程中关键工序采取了相应措施,确保了安装施工的顺利完成。
The river-crossing of Datuan~Huinan section in the second phase of Dailu Waterway Improvement Project in Shanghai is a steel tied-arch bridge.Combined with the construction environment,the main construction techniques of steel tied arch bridge are introduced in detail,and the key points and dificulties in the construction process are analyzed and summarized.In the construction of the bridge,the arch was constructed after the girder and the"floating crane process"was adopted.The corresponding measures were taken in the key processes which ensure the successful completion of the installation construction.