摘要
本文通过对江西省万载县赤兴乡分散式风电场项目资料收集以及现场调查,在分析其地质环境条件基础上,进行地质灾害现状评估、预测评估与综合评估,认为评估区地质灾害危险性等级为中等,并提出了相应的防治措施和建议。
Based on the data collection and field investigation of the distributed wind farm project in Chixing Township,Wanzai County,Jiangxi Province,the present situation assessment,prediction assessment and comprehensive assessment of the geological disaster were carried out on the basis of the analysis of the geological environment conditions.It was considered that the risk level of the geological disaster in the assessment area was medium,and the corresponding prevention measures and suggestions were put forward.
作者
陈浩
徐玲
张黎
陈飞
CHEN Hao;XU Ling;ZHANG Li;CHEN Fei(Jiangxi Academy of Emergency Management Science,Nanchang 330000,Jiangxi,China;Geophysical and Geochemical Exploration Brigade of Jiangxi,Nanchang 330000,Jiangxi,China)
出处
《资源信息与工程》
2022年第5期95-98,共4页
Resource Information and Engineering
关键词
风电场
地质灾害
评估
防治措施
wind farm
geological disaster
assessment
prevention measures