结合实际工程经验,从参数的选取、设计工况及目标的明确和汽水换热与疏水设计等方面对蒸汽管道进行设计。分析认为,GC类蒸汽管道设计体系与GB2类截然不同,管道壁厚、管道跨距等计算公式均有较大差异,因此,蒸汽管道的分类划分非常关键。
Combined with actual engineering experience,the design of steam pipelines is carried out from the selection of parameters,the clarification of design conditions and objectives,and the design of steam-water heat exchange and hydrophobic design.The analysis concluded that the GC class steam piping design system is very different from the GB2 class,and the calculation formulas for pipe wall thickness and pipe span are very different,therefore,the classification of steam piping is very critical to divide.
作者
李鹏圣
Li Pengsheng(Shanghai Municipal Engineering Design and Research Institute Group Tenth Municipal Design Institute Co.,Ltd.,Lanzhou Gansu 730000)
出处
《现代工业经济和信息化》
2022年第9期34-35,38,共3页
Modern Industrial Economy and Informationization
关键词
蒸汽管道
参数选择
设计问题
steam piping
parameter selection