摘要
介绍了3号通风井施工在小断面尺寸竖井及联通隧洞施工的布置。竖井及联通隧洞出渣的设计方法,该开挖方案满足“L”型通风竖井施工,有效解决了通风竖井与主隧洞交叉施工影响,提高了整体工程建设进度。
This paper describes the construction arrangement of No.3 ventilation shaft in light section size shaft and connecting tunnel,and the design method of shaft and connecting tunnel slag discharge.The excavation scheme satisfies the construction of L-type ventilation shaft,effectively solves the cross-construction effect between ventilation shaft and main tunnel,and improves the overall construction progress.
作者
范先锋
王耀毅
曹达政
FAN Xian-feng;WANG Yao-yi;CAO Da-zheng(POWERCHINA SINOHYDRO ENGINEERING BUREAU 14 CO.,LTD.,Kunming 650041,China)
出处
《云南水力发电》
2022年第10期140-143,共4页
Yunnan Water Power
关键词
小断面
L型竖井
出渣设计
正井法
light section
L-type shaft
high slope
design of slag discharge
normal shaft method