期刊文献+

白湖农场西大圩五号泵站改建总体布置方案研究 被引量:4

Study on general layout scheme for the reconstruction of the fifth pumping station in the west of Baihu farm
下载PDF
导出
摘要 白湖农场西大圩五号泵站建成于上世纪70年代,老站平面布置中控制性建筑物多,运行方式繁琐,严重影响泵站运行效率。通过对改建工程总体布置方案的比选分析研究,确定了满足泵站规划设计和实际运行要求的合理布置,从而保障泵站正常运行,可供类似工程参考。 The fifth pumping station in the west of baihu farm was built in the 1970s,There are many controlling buildings in the layout of the old pumping station, and the operation mode is complicated,which seriously affects the operation efficiency of the pumping station. By comparing and analyzing the general layout of the reconstruction project, the reasonable layout is determined to meet the planning and design of the pumping station and the actual operation requirements, so as to ensure the normal operation of the pumping station, which can be used as a reference for similar projects.
作者 崔冬 CUI Dong(Anhui Surver and Design Institute of Water Resources and Hydropower Co.,Ltd.,Hefei 230088,China)
出处 《江淮水利科技》 2022年第3期39-42,共4页 Jianghuai Water Resources Science and Technology
关键词 泵站改建 总体布置 方案优化 运行效率 modification of pump station general layout scheme optimization operational efficiency
  • 相关文献

参考文献4

二级参考文献9

共引文献15

同被引文献18

引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部