摘要
有轨电车综合联调是在初期运营安全评估前对前期建设成果不可或缺的检验方式,直接关系到线路开通后的安全运营和关键运营服务指标能否达标。介绍了有轨电车综合联调筹备工作内容、综合联调组织实施内容、综合联调问题跟踪处理方式,分析了综合联调组织工作的特点,提出了完善综合联调组织工作的建议。
The integrated joint commissioning(JC)of tram is an indispensable test method for the early construction achievements before the initial operation safety assessment,which is directly related to the safe operation after the line is opened and whether the key operation service indicators can meet the standards.With an introduction to the contents of preparatory work for tram integrated JC,the contents of organization and implementation of the integrated JC,and the tracking and handling methods of problems in the integrated JC,the characteristics of organization work of the integrated JC are analyzed,suggestions to improve organization of tram integrated JC are put forward.
作者
张灿明
ZHANG Canming(Shanghai Keolis Public Transport Operation Management Co.,Ltd.,200070,Shanghai,China)
出处
《城市轨道交通研究》
北大核心
2022年第S01期90-93,共4页
Urban Mass Transit
关键词
有轨电车
综合联调
组织实施
tram
joint commissioning
organization and implementation