摘要 在变电站厂房梁建设和使用的过程中,大量的电气设备会带来较多的震动,应力而产生的裂缝也是常见的现象,给厂房梁的受力与荷载带来不良的影响。为了有效减少因厂房梁设计问题所引发的裂缝现象,确保电网电能生产、传输的安全性,需要进一步加强变电站厂房梁的设计,通过合理的配筋等方式,加强对变电站厂房梁裂缝的预防与控制,为变电站的正常运行打下保障基础。 In the process of transformer substation workshop beam construction and use,a large number of electrical equipment will bring more vibrations,the stress-caused cracks are also common phenomena,bringing adverse effects on the force and load of the workshop beam.In order to effectively reduce the crack phenomenon caused by the design of the workshop beam and ensure the safety of power energy production and transmission of power grid,it is necessary to further strengthen the design of transformer substation workshop beam and strengthen the prevention and control of transformer substation workshop beam crack through reasonable reinforcement,etc.,so as to lay the foundation for the normal operation of the transformer substation.
作者 陆婧 Lu Jing(Lanzhou Yineng Electric Power Design&Consulting Co.Ltd.,Lanzhou 730050,Gansu Province,China)
出处 《建筑与装饰》 2022年第21期46-48,共3页 Construction & Decoration
关键词 变电站 厂房梁 裂缝控制 土建设计 transformer substation workshop beam crack control civil construction design
  • 相关文献

参考文献5

二级参考文献18

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部