摘要 针对地源热泵BOT项目特许经营期的决策问题,以某高校地源热泵BOT项目为例,先用净现值法构建数学模型,计算项目特许经营期可行域,再利用博弈论中的Nash讨价还价理论,引入风险分配因子,构建特许经营期计算模型,最后求得特许经营期Nash均衡解。提出的决策模型均衡了项目风险与收益,提高了决策的准确性和合理性,研究结论为地源热泵行业BOT项目特许经营期的决策提供参考。 Aiming at the decision-making problem of the ground source heat pump BOT project during the franchise period,taking the ground source heat pump BOT project of a university as an example,the mathematical model was firstly constructed by using the net present value method to calculate the franchise period feasible area.By using Nash bargaining theory in game theory,the risk distribution factor is introduced,the franchise period calculation model is constructed,and the Nash equilibrium solution of franchise period is obtained.The decision model balances project risks and benefits,and improves the accuracy and rationality of decision making.The research conclusion provides reference for decision making of BOT projects in the concession period of the ground source heat pump industry.
作者 刘进军 高林朝 邢俊敏 马少魁 杜晓康 Liu Jinjun;Gao Linchao;Xing Junmin;Ma shaokui;Du Xiaokang(Henan Agricultural University,Zhengzhou,450046;Energy Research Institute of Henan Academy of Sciences,Zhengzhou,450008)
出处 《制冷与空调(四川)》 2022年第5期757-762,共6页 Refrigeration and Air Conditioning
基金 河南省重点科技攻关项目(182102210075,132102310057)。
关键词 地源热泵 BOT模式 特许经营期 博弈论 Nash讨价还价理论 Ground source heat pump The BOT mode Franchise period Game theory Nash bargaining theory
  • 相关文献

参考文献10

二级参考文献46

  • 1王先甲,全吉,刘伟兵.有限理性下的演化博弈与合作机制研究[J].系统工程理论与实践,2011,31(S1):82-93. 被引量:155
  • 2秦旋.基于CAPM的BOT项目特许期的计算模型[J].管理工程学报,2005,19(2):60-63. 被引量:52
  • 3第六届全国热力学分析与节能学术会议学术委员会.热力学分析与节能[C].北京:科学出版社,1993.199—203.
  • 4中国建筑业协会建筑节能专业委员会.建筑节能技术[C].北京:中国计划出版社,1996.234—244.
  • 5Wang SQ, Tiong RLK, Ting SK, et al. Political risks analysis of key contract clauses in China's BOT project [ J]. Journal of construction engineering and management, 1999,125(3): 190- 197.
  • 6Malini E. Build operate transfer municipal bridge projects in India [J]. Journal of management in engineering, 1999, 15(4) :51 - 58.
  • 7Devapriya KAK, Pretorius F. The economic implications of project finance arrangements for BOO/BOT power projects in Asia [ J ]. Journal of construction research, 2002, 3(2) : 285 - 309.
  • 8Yang H, Meng Q. A note on highway pricing and capacity choice in a road network under a build-operate-transfer scheme [ J ]. Transportation research part A, 2002,36 : 659 - 663.
  • 9Fredi Lokiec, Gustavo Krnnenberg. South Israel 100 million m^3/y seawater desalination facility: Build, operate and transfer (BOT) project[J]. Desalination, 2003, 156: 29- 37.
  • 10Smith Nigel, Zhao H, Zhu Y, The Huaibel power plant and its implications for the Chinese BOT market[ J ]. International journal of project management, 2004, 22: 407- 413.