转体桥合龙利用挂篮或吊架法施工,通常存在施工周期长、风险高、对既有线运营干扰大的问题,且可能使得合龙段梁底与既有线安全距离不足,利用钢壳合龙施工则一定程度上解决了上述问题。从钢壳设计、施工工艺及关键技术、栓接钢壳的技术优势等方面,全面阐述钢壳栓接封闭合龙施工技术。
The closure of the crossing-existing railway bridge erected by swing method is carried out by the travelling cradle method,which usually has disadvantages such as long construction period,great interference and high risk,and even insufficient safety distance between girder bottoms of the closure section.The proposed new type of bolted closure steel shell,in the structure determined by numerical calculation and simulation analysis,improves the construction efficiency of swivel closure,avoids high-temperature welding that results in strength reduction of the steel shell and eliminates the influence of potential difference of the OCS,besides solving the puzzle of limited space at the girder bottom in engineering applications,bringing a significant application value.
作者
孟雪俊
MENG Xuejun(China Railway 11 Bureau Group Co.,Ltd.,Wuhan Hubei 430000,China)
出处
《中国铁路》
2022年第10期85-88,共4页
China Railway
关键词
跨既有线
转体桥
钢壳合龙
栓接
连续梁
crossing the existing railway
swivel bridge
steel shell closure
bolted
continuous girder