通过对某流域3个梯级水电站水风光互补进行计算,得到风电、光伏装机规模方案1~5的弃风光率均满足小于5%的要求。再通过总费用现值比选,最终得到方案3最优。
By calculating the water-solar complementarity of 3 cascade hydropower stations in a certain basin,it is obtained that the abandoned wind-solar rates of wind power and photovoltaic installed scale schemes 1~5 all meet the requirement of less than 5%.Then,through the comparison and selection of the present value of the total cost,the three optimal schemes are finally obtained.
作者
吴淳
范国福
龚兰强
蒲小芳
WU Chun;FAN Guofu;GONG Lanqiang;PU Xiaofang(Power China Guiyang Survey and Design Research Institute Co.,Ltd.,Guiyang 550081,China)
出处
《电工技术》
2022年第19期45-47,共3页
Electric Engineering
关键词
梯级水电站
水风光
基地
cascade hydropower stations
water,wind and solar