结合某煤矿调度中心改造工程情况,分析了局部抽柱对原有结构、周边框架柱、相邻框架梁以及基础等造成的影响,提出了增大截面的加固方法,并讨论了其具体应用。
Combined with the reconstruction of a coal mine dispatching center, the influence of partial pumping column on the frame beam and foundation of the frame column surrounding the original structure is analyzed,and the reinforcement method of increasing the section is put forward,and its specific application is discussed.
作者
孙文倩
孙超
SUN Wen-qian;SUN Chao(China Coal Xi’an Design Engineering Co.,Ltd.,Xi’an,Shanxi,710054,China;China Coal Science Engineering Group Xi’an Research Institute Co.,Ltd.,Xi’an,Shanxi,710054,China)
出处
《建材技术与应用》
2022年第6期48-51,共4页
Research and Application of Building Materials
关键词
加固
增大截面加固法
结构
基础
reinforcement
increasing section reinforcement method
structure