摘要
底板与侧墙接茬部位,既是工程防水较难解决的部位,也是工程渗漏的常见部位。海南汽摩小镇(G-23地块)项目底板采用预铺式高分子自粘胶膜防水卷材,侧墙采用APF-5000非沥青基强力交叉膜自粘高分子防水卷材(APF-5000),接茬部位在传统做法的基础上进行了改进,搭接效果良好,为同类工程提供了借鉴。
The joint part between the bottom plate and the side wall is not only a difficult part for waterproofing construction,but also a common part vulnerable to leakage.Hainan Automobile and Motorcycle Town(Plot G-23)project adopts pre-laid polymer film reinforced self-adhesive waterproofing membrane for the bottom plate,and APF-5000 non-asphalt strong cross laminated film reinforced polymer self-adhesive waterproofing membrane(APF-5000)for the side wall.The practices of the joint parts have been improved on the basis of traditional methods,and the overlap effect is good.This provides a reference for similar projects.
作者
韩晓领
阚淑霞
王云洋
李心璐
Han Xiaoling;Kan Shuxia;Wang Yunyang;Li Xinlu(Keshun Waterproof Technology Co.,Ltd.,Foshan,Guangdong528300,China)
出处
《中国建筑防水》
2022年第12期41-44,共4页
China Building Waterproofing
关键词
地下工程
底板
侧墙
接茬
高分子自粘胶膜防水卷材
非沥青基自粘高分子防水卷材
underground construction
base plate
side wall
joint connection
polymer film reinforced self-adhesive waterproofing membrane
non-asphalt self-adhesive polymer waterproofing membrane