大连湾海底隧道项目曲线段管节安装测控精度分析 被引量:2

Analysis of measurement and control accuracy of tube installation in curved section of Dalian Bay Subsea Tunnel project
下载PDF
导出
摘要 大连湾海底隧道曲线段管节曲率大,安装测控精度控制难度高,对沉管进行标定时易出现距离遮挡物近,甚至不通视的情况。通过对曲线段管节一次标定、二次标定及安装测控过程中的精度及影响因素进行分析,最后算出综合误差,验证曲线段管节沉管安装精度满足设计要求。 The elbow section of Dalian Bay Subsea Tunnel has large curvature,and it is difficult to control the installation measurement and control accuracy.When calibrating the immersed tube,it is easy to get close to obstacles or even invisible.The accuracy and influencing factors in the process of primary calibration,secondary calibration and installation measurement and control of the tubes in curved section are analyzed.Finally,the comprehensive error is calculated to verify that the installation accuracy of immersed tube in elbow section meets the design requirements.
作者 徐良 张月欣 杨伟光 XU Liang;ZHANG Yue-xin;YANG Wei-guang(No.2 Engineering Co.,Ltd.of CCCC First Harbor Engineering Co.,Ltd.,Qingdao,Shandong 266071,China;Tianjin Key Laboratory of Construction,Operation and Maintenance Technologies for Underwater Tunnels,Tianjin 300461,China)
出处 《中国港湾建设》 2022年第12期67-71,共5页 China Harbour Engineering
基金 中国交建立项课题(2014-ZJKJ-06)。
关键词 海底隧道 大曲率沉管隧道 标定测量 测量精度 subsea tunnel large curvature immersed tube tunnel calibration measurement measurement accuracy