摘要
以某地下铁路工程为研究对象,通过对变形控制要求的分析,进而提出了工程暗挖隧道施工方案,并以此为基础,采用有限元分析的方式,对该方案应用效果进行了验证,以加强对既有地铁站变形的控制。
This paper takes a subway project as the research object,through the analysis of the deformation control requirements,and then puts forward the construction scheme of the project’s underground excavation tunnel,and on this basis,uses the finite element analysis method to verify the application effect of the scheme,so as to strengthen the control of the deformation of the existing subway station.
出处
《建筑技术开发》
2022年第24期72-74,共3页
Building Technology Development
关键词
地下铁路工程
暗挖隧道
地铁站
变形控制
underground railway project
cut-and-cover tunnel
metro station
deformation control