摘要
针对郑州市扬尘管控下,高层建筑二次结构施工进度工期影响的问题,提出了一种室内施工电梯的技术应用。通过实际应用案例分析与总结可知,采用室内施工电梯不但能够有效解决工期进度的问题,而且能够解决交叉施工、二次结构施工的安全性。尤其在扬尘管控下,对于工期问题,室内施工电梯能够起到了保障性的作用。
Aiming at the problem that the construction schedule of secondary structure of high-rise building is affected by dust control in Zhengzhou, this paper puts forward a technical application of indoor construction elevator. Through the analysis and summary of practical application cases, it can be seen that the indoor construction elevator can not only effectively solve the problem of construction schedule, but also solve the safety of cross construction and secondary structure construction. Especially under the dust control, the indoor construction elevator can play a supportive role in the construction period.