摘要 为摸清邯邢地区某矿各含水层的水力联系情况,并验证帷幕注浆的实际效果,开展了大气降水、含水层水位等方面的研究。结果证明,第四系含水层及地表水体与灰岩含水层之间无水力联系,第四系水和地表水不会成为矿奥灰岩地下水的补给源。矿区奥灰岩含水层的补给方式只有一种,即区域奥灰含水层的侧向补给。同时,通过对大气降水和含水层水位变化情况的研究分析,确认帷幕注浆工程有效迟滞了区域地下水对矿区的入渗补给,降低了矿区发生突水事故的概率和危害程度,为矿山安全生产提供了有利的工程及地质保障。 In order to find out the hydraulic contact of each aquifer in a mine in Hanxing area,and verify the actual effect of curtain grouting,the research on atmospheric precipitation and aquifer water level has been carried out.The results show that there is no hydraulic connection between quaternary aquifer and surface water and limestone aquifer,and quaternary water and surface water will not be the recharge source of ordovician limestone groundwater.There is only one recharge mode of ordovician limestone aquifer in mining area,i.e.lateral recharge of regional ordovician limestone aquifer.At the same time,through the study and analysis of the atmospheric precipitation and aquifer water level change,it is confirmed that the curtain grouting project has effectively delayed the infiltration and recharge of regional groundwater to the mining area,the probability and harm degree of water inrush accident in mining area are reduced,and the beneficial engineering and geological guarantee for mine safety production is provided.
作者 赵鹏飞 张阳 蔡真印 张端 方成成 Zhao Pengfei;Zhang Yang;Cai Zhenyin;Zhang Rui;Fang Chengcheng(HBIS Group Shahe Zhongguan Iron Ore Co.,Ltd.,Xingtai 054000,Hebei)
出处 《河北冶金》 2022年第12期31-35,共5页 Hebei Metallurgy
关键词 大水矿床 帷幕 注浆 水力 flood deposit curtain grouting hydraulic
  • 相关文献

参考文献8

二级参考文献54

共引文献89

同被引文献19

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部