地铁降压变电系统构成和施工调试

Composition and Construction Commissioning of the Subway Step-down Substation System
下载PDF
导出
摘要 本文以天津市6号线一期工程线路为研究对象,在分析地铁降压变电系统构成的基础上,研究各站变压器负载率和降压变电系统电力设备的耗电量,并对各降压变电系统电力设备出现的谐波电流问题进行施工调试,结果表明40座地铁车站高峰期的变压器负载率可提供充裕的供电,环控设备、冷源设备、车站照明设备的谐波电流95%概率值曲线具有明显的区别。 In order to facilitate the construction and commissioning of the subway step-down substation system,taking Tianjin Line 6 Phase I Project as the research object,based on the analysis of the composition of the subway step-down substation system,the transformer load rate and the power consumption of the power equipments of the step-down substation system at each station are studied,and the harmonic current problems of each power equipment at step-down substation system are debugged.The results show that the transformer load rate in peak period of 40 subway stations can provide sufficient power supply,and the 95% probability value curve of harmonic current of environmental control equipments,cold source equipments and station lighting equipments has obvious differences.
作者 逯雄雄 LU Xiong-xiong(China Railway 12th Bureau Group Electrification Engineering Co.,Ltd,Tianjin 300308 China)
出处 《科技创新与生产力》 2022年第12期110-112,共3页 Sci-tech Innovation and Productivity
关键词 城市轨道交通 降压变电系统 系统构成 牵引供电系统 施工调试 降压所 urban rail transit step-down substation system system composition traction power supply system construction commissioning step-down substation
  • 相关文献

参考文献8

二级参考文献36

共引文献52

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部