期刊文献+

低水头大流量长尾水隧洞调压室结构布置优化设计

Optimization design of surge chamber structure for a hydropower station with long tailrace tunnel,low head and large flow
下载PDF
导出
摘要 依托某海外水电站项目EPC投标阶段,在招标文件条款允许带方案投标的前提下,对原设计方案进行仔细研究,结合该项目低水头、大流量、超长尾水隧洞的工程特点,从提高电站运行灵活性、改善调压室水力条件、保障调节功能等方面,对尾水调压室的布置进行深化研究,提出投标阶段的设计优化方案。 In this paper,the original design scheme of a hydropower station with low head,large flow and long tailrace system is carefully studied.Combined with the engineering characteristics of the project,the layout of surge chamber is further studied from aspects including enhancement of the flexibility of power station operation,improvement of the hydraulic conditions of surge chamber and support of the regulation function.Moreover,the optimized design scheme in the bidding stage is put forward.
作者 陈念辉 王东锋 高悦 CHEN Nianhui;WANG Dongfeng;GAO Yue(PowerChina Huadong En⁃gineering Corporation Limited)
出处 《大坝与安全》 2022年第6期19-22,共4页 Dam & Safety
关键词 尾水调压室 调压隧洞 涌浪 tailrace surge chamber pressure regulating tunnel surge
  • 相关文献

参考文献5

二级参考文献28

共引文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部