结合受限条件下的桥梁桩基、承台施工实践,针对性地分析了项目施工条件与难点,通过采用安全合理的保护措施,最大限度地对周边建(构)筑物进行保护,并高效地完成了工程施工,积累了较好的施工经验。
Combined with the construction practice of bridge pile foundation and pile caps under limited conditions,the construction conditions and difficulties of the project are analyzed. By adopting safe and reasonable protection measures, the surrounding buildings(structures) are protected to the maximum extent, and the project construction is completed efficiently and good construction experience is accumulated.