分析了目前已建特高压交流输电线路工程的造价水平及设计经验,并从路径优化、细化杆塔规划、新材料及新工艺的应用、杆塔设计优化、基础设计优化等方面对下一阶段特高压交流线路工程的建设提出设计优化建议。
The cost level and design experience of the UHV AC transmission line projects currently under construction are analyzed.The design optimization suggestions are put forward for the construction of the next stage of UHV AC line engineering from the aspects of path optimization,refinement tower planning,application of new materials and new processes,tower design optimization,and foundation design optimization.
作者
张谦
刘福海
刘颢
ZHANG Qian;LIU Fuhai;LIU Hao(State Nuclear Power Planning and Design Institute Co.,Ltd.,Beijing 100095,China;State Grid Economic and Technology Research Institute Co.,Ltd.,Beijing 102209,China)
出处
《电工技术》
2022年第23期224-226,230,共4页
Electric Engineering