摘要 为保证矿山煤层连续开采,在不建造新井筒的情况下,将副斜井进行延伸,通过对水文、地质等条件的勘察,针对矿井实际情况,采取副斜井延伸综合施工方法。实践结果显示,副斜井延伸效果良好,可将工作效率提升30%左右,施工过程保证了良好的安全性,有效控制裂隙出水及排水问题。 In order to ensure the continuous mining of coal seam, the auxiliary inclined shaft is extended without building a new shaft. Through the investigation of hydrological, geological and other conditions, according to the actual situation of the mine, the auxiliary inclined shaft extension comprehensive construction method is adopted. The practical results show that the extension effect of auxiliary inclined shaft is good, and the work efficiency can be improved by about 30%. The construction process ensures good safety, and effectively controls the water and drainage problems of cracks.
作者 杜飞雄 Du Feixiong(Shanxi Coal Transportation&Marketing Group Xinzhou Co.,Ltd.Xinzhou Shanxi 034000)
出处 《晋控科学技术》 2022年第4期31-33,36,共4页 Jinneng Holding Science and Technology
关键词 煤矿开采 斜井延伸 施工技术 Coal mining Inclined shaft extension Construction technology
  • 相关文献

参考文献4

二级参考文献16

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部