摘要
以水文条件、地质条件、施工技术及地下水位等作为切入点,对深基坑出现渗漏水现象的原因展开研究,同时分析了深基坑施工过程中,水位监测的重要性。结合施工实际情况,提出科学合理的优化方法,及时发现问题所在,消除安全事故的诱因,做到防患于未然。
Starting from hydrological conditions, geological conditions, construction technology and groundwater level, this paper studies the causes of water leakage in deep foundation pit, and analyzes the importance of water level monitoring in the process of deep foundation pit construction. Combined with the actual construction situation, it puts forward a scientific and reasonable optimization method, timely find the problem, eliminate the incentive of safety accidents, so as to nip in the wind.
作者
陈杨
CHEN Yang(Changsha Metro Group Co.Ltd.,Changsha 410000,China)
出处
《工程建设与设计》
2023年第2期185-187,共3页
Construction & Design for Engineering
关键词
地铁隧道
深基坑施工
地下水位
地下水监测
渗漏水
subway tunnel
deep foundation pit construction
groundwater level
groundwater monitoring
seepage