基于SD-MOP预制构件生产成本多目标优化

The SD-MOP-based Multi-objective Optimization of Prefabricated Component Production Cost
下载PDF
导出
摘要 文章以装配式预制构件生产为研究对象,梳理影响预制构件生产成本的因素,运用系统动力学(SD)方法构建预制构件生产成本系统流图;通过灵敏度分析,得出影响预制构件生产成本的5个主要因素;通过确定预制构件生产成本目标函数及约束条件,构建基于“成本—进度”双重目标的多目标优化(MOP)模型,以获取最优生产方案。在此基础上,以某预制构件厂为实例分析验证,结果显示:优化后的预制构件生产成本、进度均得到明显改善,模型优化效果明显。 This paper takes the production of prefabricated components for assembly use as the research object,and sorts out the factors that influence the production cost of prefabricated components.System dynamics(SD)is applied to construct the cost flow diagram for prefabricated component production.With sensitivity analysis,5 major factors influencing the production cost of prefabricated component are obtained.And,by determining the cost objective function of prefabricated component production and the constraints,a model of multiobjective optimization problem(MOP)based on dual objectives of“cost-schedule”is built to acquire the optimal scheme of production.Based on the above,a factory that manufactures prefabricated component is taken for demonstration and the result shows:the cost and schedule of prefabricated component are both improved evidently,and the built model has apparent effect for optimization.
作者 王永坤 孟洁 WANG Yongkun;MENG Jie
出处 《住宅科技》 2023年第2期59-63,共5页 Housing Science
基金 辽宁省社科规划基金项目“辽宁省建筑业碳排放脱钩效应及影响因素研究”(编号:L20BGL029) 辽宁省教育厅基金项目“辽宁既有公共建筑碳排放效率及减排潜力研究”(编号:LJKR0147) “基于复杂网络演化博弈的建筑业供应链低碳协同发展对策研究”(编号:LJKMR20220708)。
关键词 装配式建筑 预制构件 生产成本 系统动力学 多目标规划 assembly building prefabricated component production cost system dynamics(SD) multi-objective planning(MOP)
  • 相关文献

参考文献13

二级参考文献82

  • 1罗岚,吴霞,黄伟.基于FCM的装配式建筑成本影响因素分析[J].建筑经济,2020,41(S02):77-82. 被引量:26
  • 2潘敏华,吴天宇,谭江山.通州台湖保障房装配式施工成本分析[J].建筑结构,2020,50(S01):658-660. 被引量:4
  • 3封浩,颜宏亮.工业化住宅技术体系研究——基于“万科”装配整体式住宅设计[J].住宅科技,2009,29(8):33-38. 被引量:21
  • 4Raz T, Shenhar A J, Dvir D. Risk management, project success, and technological uncertainty[J]. R&:D Man-agement, 2002, 32(2): 101 -109.
  • 5Li C B, Fan L H, Guo Y, et al. The Analytic Model and its application of Generalized Project Risk Analysis[C]// Proceedings of 2004 International Conference on Construction & Real Estate Management, 2004: 229-231.
  • 6Li C B, Li X. The analytic model and its application of generalized project risk elements transmission[J]. Journal of Computational Information Systems, 2008, 4(2): 671-678.
  • 7Li C B, Wang K C. The risk element transmission theory research of multi-objective risk-time-cost trade-off[J]. Computers and Mathematics with Applications, 2009, 57(11 12): 1792-1799.
  • 8Rodrigues A, Bowers J. The role of system dynamics in project management[J]. International Journal of Project Management, 1996, 14(4): 213-220.
  • 9Li H, Love P E D, Drew D S. Effects of overtime work and additional resources Engineering, Construction and Architectural Management, 2000, 7(3): 211 -220.
  • 10Park M. Model-based dynamic resource management for construction projects[J] on project cost and quality[J] Automation in Construction 2005, 14: 585-598.

共引文献201

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部