摘要 基于有限元法,对比分析了相同条件下基坑支护采用双排桩与三排桩的区别,计算表明采用三排桩进行基坑支护可减小土体与桩体的水平位移,三排桩的抗侧移刚度更大。采用三排桩后,桩体的轴力与弯矩减小,但剪力基本相同。三排桩虽然导致围护结构单项工程的造价增加,但可少用或不用内支撑缩短基坑工程总工期,其对最终造价的影响需综合测算。 Based on the finite element method, the difference between two rows of piles and three rows of piles is compared and analyzed under the same conditions. The calculation shows that the three rows of piles can greatly reduce the horizontal displacement of the soil and the pile body, and the three rows of piles have greater lateral displacement stiffness. Three-row piles reduce the axial force and bending moment of the pile, but the shear force is basically unchanged. Although the cost of the single project of the retaining structure has increased, the three-row piles can use less or no internal support, and shorten the total construction period of the foundation pit project. The impact of this method on the final cost needs to be comprehensively estimated.
作者 郁军 Yu Jun
出处 《江苏建材》 2023年第1期43-46,共4页 Jiangsu Building Materials
基金 中国铁路上海局位集团公司2022年度科研课题“浅覆土运营地铁隧道上方框架桥顶进施工关键技术研究” 上海上铁建筑工程(集团)有限公司2022年度科研课题“运营铁路下方既有框架桥拆除施工关键技术研究”联合资助。
关键词 双排桩 三排桩 基坑支护 水平位移 double row pile three row pile foundation pit support horizontal displacement
  • 相关文献

参考文献4

二级参考文献34

共引文献42

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部