公路隧道综合管沟施工工艺及控制要点

CONSTRUCTION TECHNOLOGY AND CONTROL POINTS OF INTEGRAL TRENCH IN HIGHWAY TUNNEL
下载PDF
导出
摘要 为解决寒区公路隧道消防管道的防冻问题,桓仁–集安段高速公路大路2号隧道工程首次应用综合管沟技术。文中介绍了有仰拱段综合管沟的施工工艺,主要包括仰拱开挖支护、防排水措施、管沟立模浇筑和仰拱回填。重点介绍了施工过程中的控制要点,总结了综合管沟技术在寒区公路隧道工程中应用的优势,可为综合管沟的施工和推广提供借鉴。 In order to solve the problem of anti-freezing of tunnel fire pipeline in cold area,the integrated trench technology is applied in tunnel No.2 of Huanren-Ji’an Highway for the first time.The construction technology and of integral trench with inverted arch section are introduced,which mainly includes excavation and support of inverted arch,water proof and drainage,vertical shuttering grouting of integral trench and backfilling of inverted arch.The construction control points are highlighted,and the advantages of integral trench technology are summarized,which can provide reference for the construction of integral trench.
作者 张春成 陈家欣 马伸康 李通 孔凡胜 李达强 Zhang Chun-cheng;Chen Jia-xin;Ma Shen-kang;Li Tong;Kong Fan-sheng;Li Da-qiang
出处 《建筑技术开发》 2023年第2期132-134,共3页 Building Technology Development
关键词 综合管沟 施工工艺 寒冷地区 公路隧道 integral trench construction technics cold region vehicular tunnel
  • 相关文献

参考文献11

二级参考文献68

共引文献144

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部