城市轨道交通全自动运行线路车站空调系统风水联动调试分析 被引量:1

Analysis of Station Air-conditioning System Wind-water Joint Commissioning of Urban Rail Transit FAO Lines
下载PDF
导出
摘要 以上海某轨道交通FAO(全自动运行)线路车站风水联动调试为案例,对其调试思路进行了探索,梳理出调试过程中的相关设备。将风水联动调试划分为4个主要阶段,深入总结每个阶段调试过程中的问题并提出解决方案。对建设管理方、设计单位、运营方、集成商提出了风水联动调试的合理化建议。 Taking the wind-water joint commissioning of a FAO(fully automatic operation) rail transit line station in Shanghai as study case, the commissioning ideas are explored and the relevant equipment in the commissioning process are sorted. The wind-water joint commissioning is divided into four main stages, and the problems in the commissioning process of each stage are summarized in depth and solutions are proposed. Reasonable suggestions are put forward to construction management, design unit, operator and integrator about the wind-water joint commissioning.
作者 谭玉良 TAN Yuliang(Shanghai Shentong Rail Transit Research&Consultancy Co.,Ltd.,200070,Shanghai,China)
出处 《城市轨道交通研究》 北大核心 2023年第2期116-120,共5页 Urban Mass Transit
关键词 城市轨道交通 全自动运行线路 车站空调系统 风水联动调试 urban rail transit FAO line station air-conditioning system wind-water joint commissioning
  • 相关文献

参考文献1

共引文献16

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部