期刊文献+

500kV智能变电站合并单元拆除风险控制措施

Measures for Risk Control in Dismantling Merging Units of a 500 kV Smart Substation
下载PDF
导出
摘要 由于早期投运的智能变电站合并单元质量问题日益突出,合并单元改造工作日趋重要。以江苏某500 kV智能变电站合并单元拆除改造工程为例,通过对工程改造过程的风险点分析,提出了相应的控制措施。现场工程实践表明这些措施极大地降低了改造工作的风险,显著提升了相关工作效率。 Due to the increasingly prominent quality problems in the merging units of the early smart substations, the transformation of such merging units has become more and more important. Taking a merging unit dismantlement and reconstruction project of a 500 kV smart substation in Jiangsu Province, the risk points existing in the dismantlement are analyzed and the corresponding control measures are presented. The field engineering practice shows that these measures greatly reduce the risks of reconstruction activities and significantly improve the efficiency of related activities.
作者 李云峰 周小舟 肖迈 陈昊 LI Yunfeng;ZHOU Xiaozhou;XIAO Mai;CHEN Hao(Extra-high Voltage Company of State Grid Jiangsu Electric Power Co.,Ltd.,Nanjing 211100)
出处 《电力安全技术》 2023年第2期48-50,共3页 Electric Safety Technology
基金 山东省自然科学基金项目(ZR2020ME194)。
关键词 智能变电站 合并单元 拆除改造 风险控制 smart substation merging unit dismantlement and reconstruction risk control
  • 相关文献

参考文献5

二级参考文献45

共引文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部