摘要
港深西部铁路(洪水桥-前海)是深圳湾优质发展圈规划的唯一一条跨境轨道线路。结合上位规划、既有和在建口岸布局、工程实施条件,对环境、多层次轨道交通、城市建成区及规划的影响等方面,分过境方案、通道方案两个层次对深圳段线路方案进行了研究,并最终确定过深圳湾口岸、沿东滨路方案为推荐方案。
The Hong Kong-Shenzhen West Railway(Hung Shui Kiu-Qianhai) is the only cross-border rail line planned for the Shenzhen Bay High-quality Development Circle.In combination with the upper planning,the layout of existing and under construction ports,the implementation conditions of the project,the implementation conditions of the project,the environment,multi-level rail transit,the impact on the urban built-up area and planning,the route plan of Shenzhen section was studied at two levels,namely,the transit plan and the channel plan,and finally determined the Shenzhen Bay Port and the plan along Dongbin Road as the recommended plan.
作者
王顺发
Wang Shunfa(China Railway Siyuan Survey and Design Group Co.,Ltd.,Wuhan,China)
出处
《科学技术创新》
2023年第5期167-170,共4页
Scientific and Technological Innovation
关键词
港深西部铁路
深圳段
线路方案研究
Hong Kong-Shenzhen Western Railway
Shenzhen Section
line scheme study