新型装配式混凝土结构体系在高层工业厂房中的应用研究 被引量:2

Application Research on the New Prefabricated Structural System of the High-Level Factory
下载PDF
导出
摘要 基于项目的绿色快速建造需求,提出了一种适用于高层工业厂房的免模、免支撑装配整体式框架-现浇剪力墙结构体系(由带牛腿的预制混凝土柱、现浇剪力墙、带牛腿或挑耳的预制叠合梁和预应力空心板构成的体系)。工程应用效果表明:通过在预应力空心板板顶设置后浇叠合层、布置单层双向钢筋,有效提高了楼盖整体性;通过在预应力空心板板端上部开槽,端部布置钢筋桁架或钢筋网,端部浇筑密实,避免了预应力空心板在极端工况下脱落。同时,有限元分析结果表明:通过上述构造措施还可提高楼盖的整体性和抗震性。 Based on the green and rapid construction requirements of the project,a temlate-free and support-free assembly monolithic frame-cast-in-place shear wall structure system is proposed suited for high-level factories.The structure system consists of prefabricated columns with corbels,cast-in-place shear walls,laminated beams with corbels or pick ears,and prestressed hollow-core slabs.The engineering application effect shows that laying out the cast-in-place laminated layer and single-layer two-way reinforcements on the top of the hollow-core slab can improve the floor integrity.Sloting at the upper end of the hollow-core slab and placing reinforcements truss or mesh and then pouring concrete densely can effectively prevent the hollow-core slab falling off.The finite element analysis results show that through these structural measures above can improve the integrity and seismic resistance of the floor.
作者 袁佳佳 王洪欣 陈培潮 孙占琦 祝传新 周文龙 刘飞海 YUAN Jia-jia;WANG Hong-xin;CHEN Pei-chao;SUN Zhan-qi;ZHU Chuan-xin;ZHOU Wen-long;LIU Fei-hai(China Construction Science&Technology Group Co.,Ltd.,Shenzhen 518052,China)
出处 《混凝土与水泥制品》 2023年第4期63-67,共5页 China Concrete and Cement Products
基金 中建科技集团有限公司科技研发计划项目(ZJKJ-2022-JBGS-2)。
关键词 装配整体式框架-现浇剪力墙 高层工厂 免模 免支撑 预应力空心板 Assembled monolithic frame-cast-in-place shear wall Hign-level factory Template-free Support-free Prestressed concrete hollow-core slab