摘要
个性化、立体化的建筑结构成为人们共同的追求,同时,这种复杂的建筑结构也加大了房屋建筑工程和土木工程施工设计难度。在这样的背景下,高支模模板施工技术开始被人们广泛地应用到房屋建筑和土木工程施工中。高支模施工是支模超过8 m的高空作业方式,对工程施工的精准度和安全性有着较高的要求。为此,该文以兰州新区化工园区热电联产(背压式机组)项目工业厂房的建设为研究切入点,就该工业厂房建筑工程高支模施工方案的选择、施工技术的应用等问题进行探讨,旨在能够更好地发挥出高支模施工技术在土木工程施工建设中的重要作用,促进我国土木工程的建设发展。
The personalized and three-dimensional building structure has become people's common pursuit,and at the same time,such a complex building structure also increases the difficulty of the construction design of building construction engineering and civil engineering.Under such a background,high-supported formwork construction technology has begun to be widely introduced into the construction of building construction engineering and civil engineering.High formwork construction is a mode working high above the ground with formwork of more than 8m,which has high requirements for the accuracy and safety of engineering construction.Therefore,taking the construction of the industrial plant of the cogeneration(back-pressure unit)project in Lanzhou New Area Chemical Industry Park as the research entry point,this paper discusses the selection of the high formwork construction scheme and the application of construction technology in this industrial plant construction project and other problems,aiming to better play the important role of high formwork construction technology in civil engineering construction and promote the construction and development of civil engineering in China.
作者
吴祺
WU Qi(Gansu Engineering Construction Supervision Co.,Ltd.,Lanzhou,Gansu Province,730030 China)
出处
《科技资讯》
2023年第5期90-93,共4页
Science & Technology Information
关键词
工业厂房
建筑工程
高支模
施工技术
Industrial plant
Architectural engineering
High-supported formwork
Construction technique