摘要 针对察哈素煤矿31315工作面回采过程中因长时间停采导致31315运输巷围岩变形增大的问题,通过顶板围岩裂隙发育特征实测研究了31315运输巷在停采期间的变形破坏原因,并提出了相应的解决措施。为同类条件下工作面开采时回采巷道围岩控制技术方案选择提供了依据。 Aiming at the problem of the increase in deformation of the surrounding rock of the 31315transportation lane due to long-term stoppage during the mining process of the 31315 working face of Chahasu coal mine, the cause of deformation and failure of the 31315 transportation lane during the stop of mining was studied through the actual measurement of the development characteristics of the roof surrounding rock fissures, and proposed corresponding solutions. It provides a basis for the selection of the control technology scheme for the surrounding rock of the mining roadway in the mining of the working face under the same conditions.
作者 郭庆瑞 马军强 刘敬东 余波 田灵涛 陶彦名 徐乐 张国忠 郭红军 GUO Qingrui;MA Junqiang;LIU Jingdong;YU Bo;TIAN Lingtao;TAO Yanming;XU Le;ZHANG Guozhong;GUO Hongjun(Guodian Construction Investment Inner Mongolia Energy Co.,Ltd.,Ordos 017209,China;School of Mines,China University of Mining and Technology,Xuzhou 221116,China)
出处 《煤炭技术》 CAS 北大核心 2023年第2期90-93,共4页 Coal Technology
关键词 工作面停采 钻孔窥视 围岩变形 裂隙发育 stop mining at working face drill hole peep surrounding rock deformation fissure development
  • 相关文献

参考文献10

二级参考文献215

共引文献640

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部