复杂条件下地下承压水防渗施工技术研究 被引量:1

Research on Seepage Prevention Technology of Underground Confined Water Under Complex Conditions
下载PDF
导出
摘要 根据承压水的形成原理,白俄罗斯维捷布斯克水电站采用大围堰套小围堰的方式解决深基坑白云岩破碎带地下承压水防渗问题,厂房部位二次防渗采用素混凝土桩、高压旋喷灌浆和帷幕灌浆联合的方法进行防渗处理,有效地解决了深基坑、大面积、地质条件复杂情况下,砂卵石、白云岩破碎带地下承压水防渗问题。 According to the formation principle of confined water,Vitebsk Hydropower Station in Belarus adopts the method of large cofferdam with small cofferdam to solve the seepage prevention problem of underground confined water in dolomite broken zone of deep foundation pit.The secondary anti-seepage treatment of plant parts is carried out by the combined method of plain concrete pile,high pressure rotary grouting and curtain grouting,which can effectively solve the anti-seepage problem of underground confined water in the broken zone of sand pebble and dolomite under the condition of deep foundation pit,large area and complex geological conditions.
作者 何卫安 HE Wei-an(Sinohydro Bureau 9 Co.Ltd.,Guiyang 550001,China)
出处 《工程建设与设计》 2023年第6期132-134,共3页 Construction & Design for Engineering
关键词 地下承压水 防渗施工 技术研究 underground confined water anti-seepage construction echnology research
  • 相关文献

参考文献3

二级参考文献10

共引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部