摘要
为解决工期-成本综合优化问题,对和声搜索算法(Harmony search algorithm,HSA)的参数取值范围进行改进。首先分析了水利工程项目工期与成本估算的影响因素,构建了工期-成本集成管理模型,然后构建BIM模型提取工程量信息,同时对HSA的主要参数记忆库取值概率HMCR与和声微调概率PAR作了改进,使其参数范围更加适应工期—成本模型的取值,整个运行过程耗时短,精度高,模型经过改进后更易于实现运算,并借助MATLAB得到了工期-成本最优解。最后,以某水闸项目为例进行验证,为水利工程项目工期-成本优化探索了新的模式。
To solve the comprehensive optimization of duration-cost,the parameter range of Harmony Search Algorithm(HSA)is improved.Firstly,the influencing factors of construction period and cost estimation of water conservancy projects are analyzed,and the integrated management model of duration-cost is established.The BIM model to extract engineering quantity information is proposed.At the same time,the value probability HMCR of HSA s main parameter memory bank and the harmony fine-tuning probability PAR are improved,so that the parameter range is more suitable for the value of duration-cost model,and the whole operation process is short in time and high in precision.After the improvement,the model is easier to realize the calculation.The optimal solution of duration-cost is obtained with the help of MATLAB.Finally,a sluice project is taken as an example to verify,which provides a new idea on duration-cost optimization for water conservancy project.
作者
姚悦铃
YAO Yueling(Zhejiang Tongji Vocational College of Science and Technology,Hangzhou 311231,China)
出处
《浙江水利水电学院学报》
2023年第1期30-35,共6页
Journal of Zhejiang University of Water Resources and Electric Power
基金
浙江省水利厅2021年度水利科技项目(RC2176)。
关键词
水利工程
BIM技术
和声搜索算法(HSA)
多目标优化
water conservancy engineering
BIM technology
Harmony Search Algorithm(HSA)
multi-objective optimization