摘要
为保证软弱地层中超大矩形顶管盾构隧道近接施工安全,以某矩形顶管盾构隧道近接下穿既有高速铁路为工程背景,研究超大矩形顶管盾构隧道近接下穿高铁段不同施工加固方案的效果。结果表明:采用超前注浆可使开挖面主动失稳位移减小25.64%,被动失稳位移减小17.65%,轨道沉降减小30.38%。采用人工挖孔桩+D型钢便梁可使开挖面主动失稳位移减小51.28%,被动失稳位移减小29.41%,轨道沉降减小42.31%;现场监测表明,采用人工挖孔桩+D型钢便梁加固后轨道沉降最大值仅为1.65 mm,超大矩形顶管盾构隧道成功下穿既有高速铁路,人工挖孔桩+D型钢便梁保证了超大矩形顶管盾构隧道近接施工安全和高速铁路正常运营。
In order to ensure the safety of the adjacent construction of the super-large rectangular pipe jacking shield tunnel in the soft ground,taking a rectangular pipe jacking shield tunnel adjacently passing under the exist⁃ing high-speed railway as a study case,the effects of different construction and reinforcement schemes of the superlarge rectangular pipe jacking shield tunnel adjacent to the high-speed railway section are studied.The results show that when advanced grouting is adopted,the active instability displacement can be reduced by 25.64%,the passive instability displacement can be reduced by 17.65%,and the track settlement can be reduced by 30.38%for the ex⁃cavation face.And when the manually excavated pile+D-shaped steel auxiliary beam are adopted,the active insta⁃bility displacement can be reduced by 51.28%,the passive instability displacement can be reduced by 29.41%,and the track settlement can be reduced by 42.31%for the excavation face.Field monitoring shows that the maximum settlement of the track after reinforcement by the manually excavated pile+D-shaped steel auxiliary beam is only 1.65 mm.The super-large rectangular pipe jacking shield tunnel has successfully passed under the existing highspeed railway.The manually excavated pile+D-shaped steel auxiliary beam ensure the adjacent construction safety of the super-large rectangular pipe jacking shield tunnel and the normal operation of the high-speed railway.
作者
崔光耀
麻建飞
宁茂权
唐再兴
刘顺水
田宇航
CUI Guangyao;MA Jianfei;NING Maoquan;TANG Zaixing;LIU Shunshui;TIAN Yuhang(School of Civil Engineering,North China University of Technology,Beijing 100144;School of Civil Engineering,Beijing Jiaotong University,Beijing 100044;China Railway Fourth Survey and Design Institute Group Co.,Ltd.,Wuhan 430064;Haixia(Fujian)Transportation Engineering Design Co.,Ltd.,Fuzhou 350004)
出处
《现代隧道技术》
CSCD
北大核心
2023年第2期178-184,共7页
Modern Tunnelling Technology
基金
国家自然科学基金项目(52178378)
中铁第四勘察设计院集团有限公司科技研究开发项目(2020K143)。
关键词
隧道工程
软弱地层
矩形顶管盾构
近接施工
加固方案
Tunnel engineering
Soft ground
Rectangular pipe jacking shield
Adjacent construction
Reinforce⁃ment scheme